On Apr 8, 2015, at 10:38 AM, Yuriy Tymchuk
<yuriy.tymchuk(a)me.com> wrote:
How do they display progress in VW?
On 08 Apr 2015, at 15:34, Alexandre Bergel
<alexandre.bergel(a)me.com> wrote:
An alternative is to have another subclass, such as RTForceBasedWithProgressBarLayout
But this is not idea, because the progress bar should be by default Pharo. And on
VisualWorks no.
Another alternative, and the cleanest one I believe, is to have event generated to every
X steps. You can have whatever you wish as a callback, moving the progress bar or not.
I have added an issue about this:
https://code.google.com/p/moose-technology/issues/detail?id=1119
Alexandre
On Apr 8, 2015, at 9:50 AM, Tudor Girba
<tudor(a)tudorgirba.com> wrote:
We need a better way of modeling that :)
Doru
On Wed, Apr 8, 2015 at 2:44 PM, Alexandre Bergel <alexandre.bergel(a)me.com> wrote:
I have cleaned a bit your code with something like:
doExecute: nodeElements
self start: nodeElements.
self isJobInstalled
ifTrue: [ self runLayoutInJob ]
ifFalse: [ self runLayoutSimply ].
alpha := 0.
nodes do: [ :e | translator translateTopLeftOf: e to: e position ]
It is in version .816 of Roassal2.
We should be able to run the layout without job. This is important for us
Thanks!
Alexandre
On Apr 7, 2015, at 5:04 PM, Peter Uhnák
<i.uhnak(a)gmail.com> wrote:
Out of curiosity I dug a little deeper and was happy to learn about a Job and more about
Pharo internals.
In any case, try replacing RTForceBasedLayout>>doExecute: with this
~~~~~~~~~~~~~~~~~~~~~~~~~
doExecute: nodeElements
self start: nodeElements.
[ :job |
job
title: 'Laying out elements';
min: 1 - alpha;
max: 1.
nbIterations = 0
ifTrue: [ [ alpha := alpha * 0.99. alpha > 0.005 ] whileTrue: [
self step. job currentValue: 1 - alpha ] ]
ifFalse: [ nbIterations timesRepeat: [ alpha := alpha * 0.99. self
step. job currentValue: 1 - alpha ] ]
] asJob run.
alpha := 0.
nodes do: [ :e | translator translateTopLeftOf: e to: e position ].
~~~~~~~~~~~~~~~~~~~~~~~~~
it's bit messy (and doesn't account for nbIterations), but its a proof of
concept.
I thing that it makes sense to create execution indicator without progress (with spinner
for example)
What can be done is to display alpha on progress bar. From current value to 0.005 or
whatever there is.
I was thinking more something like this
http://www.barchart.com/shared/images/progress_bar.gif or thsi
https://i.stack.imgur.com/gz9GK.gif
Peter
_______________________________________________
Moose-dev mailing list
Moose-dev(a)iam.unibe.ch
https://www.iam.unibe.ch/mailman/listinfo/moose-dev
--
_,.;:~^~:;._,.;:~^~:;._,.;:~^~:;._,.;:~^~:;._,.;:
Alexandre Bergel
http://www.bergel.eu
^~:;._,.;:~^~:;._,.;:~^~:;._,.;:~^~:;._,.;:~^~:;.
_______________________________________________
Moose-dev mailing list
Moose-dev(a)iam.unibe.ch
https://www.iam.unibe.ch/mailman/listinfo/moose-dev
--
www.tudorgirba.com
"Every thing has its own flow"
_______________________________________________
Moose-dev mailing list
Moose-dev(a)iam.unibe.ch
https://www.iam.unibe.ch/mailman/listinfo/moose-dev
--
_,.;:~^~:;._,.;:~^~:;._,.;:~^~:;._,.;:~^~:;._,.;:
Alexandre Bergel
http://www.bergel.eu
^~:;._,.;:~^~:;._,.;:~^~:;._,.;:~^~:;._,.;:~^~:;.
_______________________________________________
Moose-dev mailing list
Moose-dev(a)iam.unibe.ch
https://www.iam.unibe.ch/mailman/listinfo/moose-dev
_______________________________________________
Moose-dev mailing list
Moose-dev(a)iam.unibe.ch